| DIRECTIVE NUMBER: STD 3-0.1A |
EFFECTIVE DATE: June 18,
1999 |
| SUBJECT: Plain Language Revision of OSHA
Instruction STD 3.1, Interim Fall Protection Compliance Guidelines
for Residential Construction |
ABSTRACT
| Purpose: |
This Instruction is a plain language re-write of OSHA
Instruction STD 3.1, the Agency's interim enforcement policy on fall
protection for certain residential construction activities. |
| |
|
| Scope: |
OSHA-wide |
| |
|
| References: |
29 CFR Part 1926 Subpart M |
| |
|
| Cancellations: |
OSHA Instruction STD 3.1, Interim Fall Protection Compliance
Guidelines for Residential Construction, dated December 8,
1995. |
| |
|
| State Plan Impact: |
None |
| |
|
| Action Offices: |
National, Regional and Area Offices |
| |
|
| Originating Office: |
Directorate of Construction |
| |
|
| Contact: |
Garvin M. Branch (202) 693-2345 Directorate of Construction
N3621, FPB 200 Constitution Ave., N.W. Washington, DC
20210 |
By and Under the Authority of R. Davis Layne Deputy Assistant
Secretary, OSHA

TABLE OF CONTENTS
- PURPOSE.
- SCOPE.
- CANCELLATION.
- REFERENCE.
- ACTION
INFORMATION.
- Responsible Office.
- Action Offices.
- Information Offices.
- FEDERAL
PROGRAM CHANGE.
- BACKGROUND.
- AVAILABILITY
OF ALTERNATIVE PROCEDURES
- Definition of "residential construction."
- Listed Activities and Alternative Procedures.
- Questions.
- ALTERNATIVE
PROCEDURES FOR GROUP 1: INSTALLATION OF FLOOR JOISTS, FLOOR
SHEATHING, AND ROOF SHEATHING; ERECTING EXTERIOR WALLS; SETTING AND
BRACING ROOF TRUSSES AND RAFTERS.
- General Requirements For Group 1 Activities.
- Additional Requirements For Specific Group (1) Activities.
- ALTERNATIVE
PROCEDURES FOR GROUP 2: WORKING ON CONCRETE AND BLOCK FOUNDATION
WALLS AND RELATED FORMWORK.
- Trained Workers Only.
- Adequate Support.
- Bad Weather.
- Staging of Materials/Equipment.
- Impalement Hazards.
- ALTERNATIVE
PROCEDURES FOR GROUP 3: THIS GROUP CONSISTS OF THE FOLLOWING
ACTIVITIES WHEN PERFORMED IN ATTICS AND ON ROOFS:
INSTALLING DRYWALL, INSULATION, HVAC SYSTEMS, ELECTRICAL SYSTEMS
(INCLUDING ALARMS, TELEPHONE LINES, AND CABLE TV), PLUMBING AND
CARPENTRY.
- Trained Workers Only.
- Staging of Materials.
- Impalement Hazards.
- Restricted Access.
- Bad Weather.
- ALTERNATIVE
PROCEDURES FOR GROUP 4: ROOFING WORK (REMOVAL, REPAIR, OR
INSTALLATION OF WEATHERPROOFING ROOFING MATERIALS SUCH AS SHINGLES, TILE
AND TAR PAPER).
- General Requirements.
- Safety Monitors and Slide Guards (for roofs with an eave height of
up to and including 25 feet).
- Slide Guards: Requirements for Materials, Configuration and
Installation.
- CITATION
POLICY.
INDEX

- PURPOSE.
- This Instruction is a plain language re-write of OSHA Instruction
STD 3.1, the Agency's interim enforcement policy on fall protection
for certain residential construction activities.
- Fall protection requirements for residential construction are set
out in 29 CFR 1926.501(b)(13). In general, that provision requires
conventional fall protection for work at or over six feet. However,
OSHA Instruction STD 3.1 modifies those requirements. It permits
employers engaged in certain residential construction activities to
use alternative procedures routinely instead of conventional fall
protection. No showing of infeasibility of conventional fall
protection is needed before using these procedures. A fall protection
plan is required but it does not have to be written nor does it have
to be specific to the jobsite. Different alternative procedures are
specified for different activities.
- SCOPE. This Instruction applies OSHA-Wide.
- CANCELLATION. OSHA Instruction STD 3.1,
Interim Fall Protection Compliance Guidelines for Residential
Construction, dated December 8, 1995, is cancelled.
- REFERENCE. 29 CFR Part 1926 Subpart M.
- ACTION INFORMATION.
- Responsible Office. Directorate of Construction.
- Action Offices. National, Regional, and Area Offices
- Information Offices. State Plan Offices, Consultation
Project Managers
- FEDERAL PROGRAM CHANGE. This Notice describes a
Federal OSHA program change for which State adoption is not required.
- BACKGROUND. On December 8, 1995 OSHA
published an interim fall protection compliance policy for fall
protection for certain residential construction activities, pending
further rulemaking on Subpart M. This Notice is a plain language
re-write of that policy; it does not make substantive changes to the
policy. The Agency will solicit public comment on fall protection issues
in residential construction in an Advance Notice of Proposed Rulemaking
on Subpart M. After analyzing those comments, we will re-evaluate this
policy.
- AVAILABILITY OF ALTERNATIVE PROCEDURES.
Alternative procedures are available to employers who are (1) engaged in
residential construction, and (2) doing one of the listed activities.
- Definition of "residential construction."
- For purposes of this instruction, an employer is engaged in
residential construction where the working environment, materials,
methods and procedures are essentially the same as those used in
building a typical single-family home or townhouse.
- Residential construction is characterized by:
 | Materials: Wood framing (not steel or concrete); wooden floor
joists and roof structures.
 | Methods: Traditional wood frame construction techniques.
| |
- In addition, the construction of a discrete part of a large
commercial building (not the entire building), such as a wood frame,
shingled entranceway to a mall, may fit within the definition of
residential construction. Such discrete parts of a commercial
building would qualify as residential construction where the
characteristics listed above are present.
- Listed Activities and Alternative Procedures.
There are four groups of residential construction activities for
which alternative fall protection plans are available. Each group has
its own set of alternative procedures and will be discussed in
Sections IX through XII. The groups are:
- GROUP 1. Installation of floor joists, floor sheathing, and roof
sheathing; erecting exterior walls; setting and bracing roof trusses
and rafters.
- GROUP 2. Working on concrete and block foundation walls and
related formwork.
- GROUP 3. This group consists of the following activities when performed in attics and on roofs: installing
drywall, insulation, HVAC systems, electrical systems (including
alarms, telephone lines, and cable TV), plumbing and carpentry.
- GROUP 4. Roofing work (removal, repair, or installation of
weatherproofing roofing materials such as shingles, tile and tar
paper).
- Questions.
 | Do any of these plans have to be written and site specific? No.
 | Does the employer have to determine that conventional fall
protection is infeasible before being permitted to use an
alternative procedure? No.
| |
- ALTERNATIVE PROCEDURES FOR GROUP 1:
INSTALLATION OF FLOOR JOISTS, FLOOR SHEATHING, AND ROOF SHEATHING;
ERECTING EXTERIOR WALLS; SETTING AND BRACING ROOF TRUSSES AND RAFTERS.
The alternative measures for this group are set out in Appendix E to
Subpart M. Appendix E requires the employer to implement a Fall
Protection Plan. Such a plan must lay out the safest procedures to be
followed at the work site to prevent falls. Although the plan need not
be in writing, it must be communicated to all employees on site who
might be subject to fall hazards.
NOTE: Height Limitation: The Appendix E plan may only be used on
structures up to three and a half stories or 48 feet (including
basement, two finished levels, attic). The 48' measure is from the base
of the building, at the lowest ground level (including any excavation),
to the point of greatest height. The following are the required elements
of the Plan:
- General Requirements For Group 1 Activities. Training,
Implementation/ Supervision By Designated Individuals, Controlled
Access Zones, Plan Administration (required for all Group 1
activities).
- Training
Each employee performing work in Group 1 activities must be
trained in the requirements of the Plan. The employer must ensure
that the employees (1) understand the procedures and follow the
instructions of the crew supervisor or foreman; (2) are able to
recognize unsafe/hazardous conditions and are to report them to the
employer; (3) can recognize when compliance with the Plan would
create a greater hazard and are instructed to inform the Competent
Person before proceeding when that occurs. Training and retraining
violations shall be cited under 29 CFR 1926.503(a) and 1926.503(c).
Subsection 1926.503 (b) may not be cited for residential
construction.
NOTE: Any concerns raised by employees at any time during
construction must be addressed (determined to be valid or not)
before work proceeds.
- Implementation/Supervision.
a. Competent Person. The employer must designate a Competent
Person, who will be charged with implementing the Plan. The
Competent Person must continually monitor compliance with the Plan,
including the provision of training and the proper use of Controlled
Access Zones.
b. Qualified Person. The employer must designate a qualified
person to approve any changes to the Plan.
c. Crew Supervisor/Foreman. The employer must designate a crew
supervisor or foreman and charge him or her with the responsibility
of immediately correcting any unsafe practice or condition.
- Controlled Access Zones.
For purposes of this Instruction, a Controlled Access Zone (CAZ)
restricts access to a clearly designated area where a Group One
activity (installation of floor joists, floor sheathing, roof
sheathing; erecting exterior walls; setting and bracing roof trusses
and rafters) is taking place. The CAZ must meet the following
requirements:
a. Boundaries. The competent person shall determine the
boundaries of the CAZ and clearly mark them with signs, wires,
tapes, ropes or chains.
b. Monitor. The crew supervisor/foreman shall monitor the
workers in the CAZ to ensure that they do not engage in unsafe
practices.
c. Restricted Access. Access to the CAZ must be restricted to
authorized entrants. An authorized entrant is a worker who has
received the training described above. The competent person must
identify each entrant as an authorized entrant after the employee
has successfully completed the training.
d. Final Check. Before work begins in the CAZ, the competent
person must ensure that all protective measures in the Plan have
been implemented.
- Plan Administration.
- Employer Enforcement.
The employer is required to enforce
the Plan. The crew supervisor/foreman, as well as individuals in
the Safety and Personnel Department, must have the right to issue
disciplinary warnings to employees, up to and including
termination, for failure to follow the requirements of the Plan.
Unsafe practices or conditions must be corrected immediately.
- Changes To The Plan.
-- Designation of
qualified person: the employer must designate a qualified
person to approve changes to the Plan. -- Approval required: changes to the Plan may not
be made unless approved by the qualified person. -- Plan Review: the qualified person must review
the Plan as the job progresses to determine if additional
practices, procedures or training need to be implemented. The
employer shall notify and, if necessary, train workers in the new
procedures.
- Accident Investigations/Plan Review.
All accidents
resulting in injury to workers shall be reported and investigated.
To help prevent further accidents, the investigation must be
documented so that the cause and means of prevention can be
identified. In the event of a fall or other serious incident, the
Plan shall be reviewed to determine if additional practices,
procedures, or training need to be implemented.
- Additional Requirements For Specific Group (1) Activities.
- Installing Roof Trusses and Erecting Rafters.
- Walls Up To 8 Feet.
Interior scaffolds must be installed
along the interior wall, below the area where the trusses/rafters
will be located. This can often be accomplished with "sawhorse"
scaffolds constructed of 46 inch sawhorses and 2 x 10 planks.
- Walls Over 8 Feet.
If using scaffolds and ladders
throughout the process would create a greater hazard, the
following general requirements and specific
procedures apply.
(1). Walls over 8 feet. General requirements.
(a)Falling Objects/Restricted Access. Once truss/rafter
installation begins, workers not involved in that activity shall
not stand or walk below or adjacent to the roof opening or
exterior walls in any area where they could be struck by falling
objects.
(b) Bracing. Trusses/rafters must be adequately braced
before any worker may use them as a support.
(c) Designated, Trained Workers. The employer must designate
the trained workers who will work on the top plate, and those who
will work on the peak.
(d) Restricted Duties. Top plate workers shall have no other
duties during truss/rafter erection.
(2) Procedures for working on the top plate.
(a) Installing The First Two Trusses. The first two
trusses/rafters must be set from ladders. The ladders must lean on
side walls at points where the walls can support the load imposed
by the ladder and worker. After the first two trusses/rafters have
been set, a worker will climb a ladder onto the interior top plate
to secure their peaks.
(b) Remain On The Top Plate. Workers will remain on the top
plate and use the previously stabilized trusses/rafters as support
while the other trusses/rafters are erected.
(3) Procedures for working at the peak.
(a) When Workers May Work On Peaks/Ridge Beam. Workers
detaching trusses from cranes or securing trusses at the peaks may
be positioned at the peak of the trusses/rafters. Workers may be
stationed on the top of the ridge beam where that is the only
feasible way to secure rafters to the ridge beam.
(b) Stable Work Position Workers at the peak, in the web of
trusses, or on top of the ridge beam shall work from a stable
position. They must either sit on a ridge seat (or the equivalent)
or position themselves in previously stabilized trusses/rafters
and lean into, and reach through, the trusses/rafters.
(c) Limited Fall Hazard Exposure. Workers must not remain on
or in the peak/ridge any longer than necessary to complete the
task safely.
- Roof Sheathing Operations. The competent person must determine
when the roof system is stable enough to support a conventional fall
protection system anchorage. The following provisions apply until
the roof system can be used as an anchorage point; at that time
personal fall arrest systems must be used.
- Qualified Workers.
Only qualified workers shall install
roof sheathing.
- Secure Footing/Weather.
The employer must ensure that
workers remove slip hazards before walking on sheathing. Such
measures include removing mud from shoes or boots. When wet
weather is present, roof sheathing shall be suspended unless safe
footing can be assured. If winds exceed 40 miles per hour,
sheathing operations are to be suspended, unless wind breakers are
erected.
- Staging of Materials.
To minimize exposure to fall hazards,
materials must be staged so that workers on the roof have quick
and safe access to them.
- Falling Objects/Restricted Access.
Workers not involved in
roof sheathing shall not stand or walk below or adjacent to the
roof opening or exterior walls where they could be struck by
falling objects. The competent person shall clearly designate the
restricted area before placement of the first piece of sheathing.
The competent person may order a brief halt to the sheathing work
to allow other workers to pass through the restricted area, as
long as suspending work does not create a greater hazard.
- Slide Guards.
-- Bottom Row: The bottom row of roof
sheathing may be installed by workers standing in truss webs and
leaning over the sheathing. After the bottom row is installed, a
slide guard of at least four (4) inches nominal in height shall be
securely attached to the roof. It must extend across the full
width of the roof.
-- Slide Guard Intervals: Roof Pitch Up To
(and including) 9 in 12: Additional slide guards are required
at 13 foot intervals as successive rows of sheathing are
installed.
-- Slide Guard Intervals: Roof Pitch Over 9 in
12: Additional slide guards are required at four foot
intervals.
NOTE: These slideguard requirements, which come from Appendix
E, differ from those for Group 4 Activities (roofing
work).
- Installation of Floor Joists and Floor Sheathing.
- Designated, Trained Workers.
The employer must designate
the trained workers who will do this work.
- Staging of Materials.
To minimize exposure to fall hazards,
materials must be staged so that workers have quick and safe
access to them.
- Restricted Access.
While this work is taking place, workers
not directly assisting in it shall not be permitted within six (6)
feet of the leading edge.
- Installation Process: Floor Joists/Trusses.
The first floor
joist or truss must be rolled into position and secured by workers
on the ground, ladders, or sawhorse scaffolds. Successive
joists/trusses must be rolled into place. They are then to be
secured from a platform. The platform is to be built from a sheet
of plywood laid over the previously secured floor joists or
trusses.
- Installation Process: Floor Sheathing.
The first row of
floor sheathing must be installed by workers on the ground,
ladders, or sawhorse scaffolds. After the first row of sheathing
has been installed, workers shall work from the established deck.
- Erection of Exterior Walls.
- Designated, Trained Workers.
The employer must designate
the trained workers who will do this work.
- Warning Line.
A painted warning line six (6) feet from the
perimeter will be clearly marked before any wall erection
activities take place.
NOTE: As discussed above, this work must be done within a CAZ.
A crew supervisor/foreman is required to monitor this work and
warn anyone who approaches the unprotected edge. The warning line
does not replace the monitor; it is an additional safety
measure.
- Staging of Materials.
To minimize exposure to fall hazards,
materials must be staged so that workers have quick and safe
access to them.
- Limit Fall Hazard Exposure.
Workers constructing exterior
walls shall complete as much cutting of materials and other
preparatory work as possible away from the edge of the deck.
NOTE: Wall openings (more
than six feet above the lower level), floor holes and roof holes:
As soon as sheathing has been installed around a floor hole, roof
hole, or wall opening that is not going to be sheathed (such as a hole
for a doorway, stairwell or skylight), it must be covered, or
protected by a guardrail.
- ALTERNATIVE PROCEDURES FOR GROUP 2:
WORKING ON CONCRETE AND BLOCK FOUNDATION WALLS AND RELATED FORMWORK.
This Instruction specifies the alternative procedures for protecting
employees working from the top surface of block foundation walls,
concrete foundation walls, and related form work. These procedures
are:
- Trained Workers Only.
Only trained workers shall be allowed to
work on the top of the foundation wall/form work, and only as
necessary to complete the construction of the wall.
- Adequate Support.
All formwork shall be adequately supported
before any worker may work on top of the form work.
- Bad Weather.
When adverse weather (such as high winds, rain,
snow, or sleet) creates a hazardous condition, operations shall be
suspended until the hazardous condition no longer exists.
- Staging of Materials/Equipment.
Materials and equipment for the
work shall be conveniently located to the workers on the top of the
foundation/formwork.
- Impalement Hazards.
Materials and other objects which could
pose impalement hazards shall be kept out of the area below where
workers are working or shall be properly guarded.
- ALTERNATIVE PROCEDURES FOR GROUP 3:
THIS GROUP CONSISTS OF THE FOLLOWING ACTIVITIES WHEN
PERFORMED IN ATTICS AND ON ROOFS: INSTALLING DRYWALL, INSULATION,
HVAC SYSTEMS, ELECTRICAL SYSTEMS (INCLUDING ALARMS, TELEPHONE LINES, AND
CABLE TV), PLUMBING AND CARPENTRY.
This Instruction specifies the procedures for this group. They
are:
- Trained Workers Only.
Only trained workers shall be allowed to
work in attics and on roofs, and only as necessary to complete the
construction of the system being installed.
- Staging of Materials.
Materials and equipment for the work
shall be located conveniently close to the workers.
- Impalement Hazards.
Materials and other objects which could
pose impalement hazards shall be keep out of the area below where
workers are working, or properly guarded.
- Restricted Access.
While attic or roof work is in progress,
workers not involved in such work shall not stand or walk below or
adjacent to any openings in the ceiling where they could be struck by
falling objects.
- Bad Weather.
When adverse weather (such as high winds, rain,
snow, or sleet) creates a hazardous condition, operations shall be
suspended until the hazardous condition no longer exists.
NOTE: The provisions of this Instruction do not apply to interior
finishing work when done outside of attics or roofs areas. Subpart M
applies to such work with respect to stairways, stairway openings,
walkways, floor or window openings, floor holes or other elevated
openings or open sides.
- ALTERNATIVE PROCEDURES FOR GROUP 4:
ROOFING WORK (REMOVAL, REPAIR, OR INSTALLATION OF WEATHERPROOFING
ROOFING MATERIALS SUCH AS SHINGLES, TILE AND TAR PAPER).
Restriction on Application for Roofing Work. The alternative
procedures in this Instruction may only be used for this work where: (a)
the roof slope is 8 in 12 or less, and (b) the fall
distance, measured from the eave to the ground level, is 25 feet or
less.
- General Requirements.
- Trained Workers Only.
Only workers who have been trained to
be proficient in the alternative methods of fall protection shall be
allowed onto the roof. In addition, each affected employee shall be
trained to ensure specific awareness of the fall hazards associated
with work on roofs with rake edges ("rake edges" are inclined roof
edges, such as those on the gable end of a building).
- Slip Hazards
The roof surfaces shall be inspected for
slipping hazards. The employer shall either eliminate any such
hazards or take effective measures to have workers avoid them. The
employer shall have workers wear appropriate footwear to reduce the
potential for slipping.
- Bad Weather.
When adverse weather (such as high winds, rain,
snow, or sleet) creates a hazardous condition, roofing operations
shall be suspended until the hazardous condition no longer exists.
- Roof holes/openings.
The employer shall have any damaged
portions of the roof deck repaired as soon as practicable. Any holes
(including skylight openings) or other areas where employees would
not have safe footing shall be covered or surrounded by guardrails
that comply with the requirements of 1926.502.
- Ladders/Scaffolds.
If ladders or scaffolds are used, they
shall be erected and maintained in accordance with the requirements
of Subparts X and L of OSHA's construction standards. In addition,
employees shall be trained in accordance with the requirements of
Subparts X & L.
- Access To Roof.
Employers shall not allow workers to ascend
or descend the roof's slope within 6 feet of the rake edge except
where that limitation would prevent the performance of work.
- Location of Materials.
Supplies and materials shall not be
stored within 6 feet of the rake edge, or three feet where tile roof
systems are being installed.
- Impalement Hazards.
The area below the eaves and rakes shall
be kept clear of materials and other objects which could pose
impalement or other hazards, or properly guarded.
- Safety Monitors and Slide Guards (for roofs with an eave height of
up to and including 25 feet).
- Roof Slope (Any Roof Type): Up to 4 in 12. The employer must use
either a safety monitoring system that complies with ?1926.502, or
roofing slide guards. If slide guards are used, they must be built
and installed in accordance with the requirements set out below.
- Roof Slope (Except Tile or Metal Roofs): Over 4 in 12 (and up to
8 in 12): Slide guards are required.
- Roof Slope (Tile or Metal Roofs): Up to (and including) 8 in 12:
The safety monitoring system may be used instead of slide guards.
- Roof Slope (Any Roof Type): Over 8 in 12: Alternatives to the
requirements of the standards are not available.
- Eave Height Over 25 feet (Any Slope, Any Roof Type):
Alternatives to the requirements of the standards are not available.
- Slide Guards: Requirements for Materials, Configuration and
Installation.
- Roof Slope: 6 in 12 or less:
- Material. All slide guards must be constructed of 2"x 6"
(nominal) stock.
- Installation. No more than three rows of roofing material
(installed across the lower eave) shall be applied before
installing the slide guards. The roof jacks (or similar supports)
shall be installed using nails long enough to withstand an
employee sliding into the guard.
- Configuration. The face of the slide guard must be
perpendicular (about 90 degrees) to the surface of the roof. There
must be continuous slide guards along the eave.
- Roof Slope: Over 6 in 12 (up to and including 8 in 12):
- Material: 2"x 6" stock.
- Installation: Continuous slide guards shall be installed along
the eave, as described above. Additional slide guards shall be
installed below each work area at intervals not to exceed eight
feet. They shall be installed using the following procedure: the
employee, while standing on the slide guard below, secures the
roof jacks for the next slide guard with nails and then installs
the planks. The employee then climbs up to the new slide guard to
continue the roofing work. This sequence is repeated as work
proceeds up the roof.
- Configuration: The continuous slide guards at the eave must be
at about 90 degrees to the roof surface, as described above. The
additional slide guards need not be continuous -- but they must be
long enough to protect the work area. They do not have to be at 90
degrees to the roof surface.
- Removal: Once the roofing material is installed to the ridge,
the employee is to climb down to the next lower slide guard and
remove the upper slide guard. The employee repeats this process
down the roof until all the slide guards are removed. Only when
the roofing job is completed may the slide guards at the eave be
removed.
- CITATION POLICY.
If an employer (engaged in residential construction) does not provide
conventional fall protection, the compliance officer must determine if
STD 3-0.1a provides alternative procedures for the activity in question.
If alternative procedures are available, the compliance officer must
determine if they have been implemented. If there is a deficiency in the
implementation of the alternative procedures, the fall hazard shall be
cited as a violation of 1926.501(b)(13). No other provision may be cited
for a fall hazard addressed by 1926.501(b)(13). Deficiencies in training
required by 1926.20 may also be cited where appropriate.

INDEX
1926.501(b)(13)
Adverse Weather
Bad Weather
Ladders or Scaffolds
Roof Slope
Slide Guards
Trained Workers |